Texas Instruments TPS55010EVM-009 Evaluation Module

Texas Instruments TPS55010EVM-009 Evaluation Module is a fully assembled and tested circuit for evaluating the TPS55010 isolated DC/DC converter with integrated FETs. The TPS55010EVM-009 uses fixed frequency current mode control and a half-bridge power stage with primary-side feedback to regulate the output voltage for power levels up to 2W. This evaluation module features isolated flybuck topology, primary-side feedback, and 100kHz to 2000kHz switching frequency. The Texas Instruments TPS55010EVM-009 synchronizes to an external clock and has an adjustable slow start and adjust voltage UVLO.

Features

  • Isolated Flybuck Topology
  • Primary Side Feedback
  • 100kHz to 2000kHz Switching Frequency
  • Synchronizes to External Clock
  • Adjustable Slow Start
  • Adjustable Input Voltage UVLO
  • Open Drain Fault Output
  • Cycle-by-Cycle Current Limit
  • Thermal Shutdown Protection
  • 3mm×3mm 16-Pin QFN Package

Applications

  • Floating Supplies for IGBT Gate Drivers
  • Noise Immunity in PLCs, Data Acquisition and Measurement Equipment
  • Isolated RS-232 and RS-485 Communication Channels
  • Powers Line Drivers, ISO Amplifiers, Sensors, CAN Transceivers
  • Promotes Safety in Medical Equipment

Functional Diagram

Block Diagram - Texas Instruments TPS55010EVM-009 Evaluation Module
公開: 2012-01-27 | 更新済み: 2022-03-11